Jon Shaw is a highly experienced and busy specialist construction and engineering barrister with extensive experience in handling lower value and multi-million pound claims. These have included:
Construction of a new transport interchange facility in North West England: lead a ‘Value recovery team’ and prepared several individual claim documents relating to prolongation, delay and disruption and associated costs. Dispute value: £6.5million
Construction of new road and bridges in North West England: Preparation of an initial claim document requesting an extension of time and associated costs. Dispute value: £900,000
Sewer replacement in North West England: Preparation of a claim for additional entitlement. Negotiation and settlement with main contractor. Contract value: £370,000
Container Port in South East England: pre-contract reports giving opinion in respect of risks and opportunities of potential contractual arrangements. Advice covered contract interpretation, delay, liabilities, insurances, causation issues. Dispute value: £20million
Installation of utilities in Central London: Advice, preparation, disclosure, instruction of counsel, overall supervision and trial. Dispute value: £5million
UK tram service repairs: Advice, preparation, disclosure, appointment of experts and overall supervision. Dispute value: £8.5million
Utilities Infrastructure Network and a £750 million 5-year Framework Contract: Preparation of a various opinions and reports re: measurement issues, contractual matters and claims
Upgrade works to rail network in South England: Preparation of a report highlighting the risks and opportunities of a contractual arrangement. Contract value: £22million
Construction of a new by-pass road in the Midlands: Preparation of a report giving opinion in respect of specific contractual issues. Contract value £2.9million
Refurbishment of water treatment works in North West England: Preparation of a report giving opinion in respect of specific contractual issues and potential sources of dispute. Contract value £4.4million
Adjudication experience
Jon has acted in many adjudications including:
Design and installation of power-generation equipment in North West England: Preparation of a referral and reply in respect of the contractual interpretation of limitation to a liability clause. Dispute value: £450,000
Civil engineering works associated with an office development in North West England: Preparation of a response submission and client representation during proceedings. Dispute value: £300,000
Construction of a new road and bridges in North West England: Preparation of submissions for adjudication proceedings requesting an extension of time and associated costs. Dispute value: £900,000
Other valuation, payment and final account adjudications: acting in many such cases for multiple parties in these adjudications.
Arbitration experience
Jon is has experience in construction arbitrations. These have included:
Hospital build project in North Wales: Assistance with the preparation of a statement of case for delay and associated additional cost. Dispute value: £1.2million
UK Tram project: Acting as the UK Team Leader defending discrete set-off claims in arbitration proceedings. Dispute value of £8million and defending delay claim in arbitration proceedings. Dispute value: £24million
Expert Witness support
Jon is a highly-respected adviser for expert witnesses in their report preparation and in giving consultancy support to quantum experts. Work has included:
Industrial estate development in North England: Assistance given to the expert witness in the preparation of an expert report in respect of planning and quantum aspects Dispute value £420,000
Autoclave Construction in North England: Assistance given to the expert witness in the preparation of an expert report in respect of planning and quantum aspects. Dispute value £820,000
Hospital building project in North Wales: Assistance provided to the quantum expert in preparing the variation account aspect of a report. Dispute value: £1.2million